Past Construction Updates

Construction Updates

 

ENTRANCE AND COURTYARD (Northwest Side)

August 6, 2026

ENTRANCE AND COURTYARD (Northwest Side)
The first exterior panels are being added, bringing color and character to the entrance and showcasing the building's emerging design.
ENTRANCE (North Side)

August 6, 2026

ENTRANCE (North Side)
Furring strips are being installed at the main entrance, creating the foundation for the colorful exterior panels that will soon define the building's look.
ENTRANCE, CLASSROOM/CONFERENCE ROOM AND LAB (Northeast Side)

August 6, 2026

ENTRANCE, CLASSROOM/CONFERENCE ROOM AND LAB (Northeast Side)
Natural-looking brick details are taking shape on the exterior of the future classroom/conference room and lab, bringing texture and character to the facility.
ENTRANCE AND COURTYARD (West Side)

July 29, 2026

ENTRANCE AND COURTYARD (West Side)
Sheathing continues around the building to the courtyard structure.
ENTRANCE (North Side)

July 29, 2026

ENTRANCE (North Side)
With sheathing nearly complete, the entrance is ready for the next transformation; the addition of one of its signature colors.
CLASSROOM/CONFERENCE ROOM AND LABS (East Side)

July 29, 2026

CLASSROOM/CONFERENCE ROOM AND LAB (East Side)

Progress continues as the east side of the building is being prepared for the upcoming masonry installation.
OUTER INSULATION ALMOST COMPLETE

May 4, 2026

OUTER INSULATION ALMOST COMPLETE
Wrapping up the exterior! Insulation is nearly complete as the building continues to transform.
OUTER INSULATION BEING INSTALLED

April 6, 2026

OUTER INSULATION BEING INSTALLED
Work has begun on insulating the building's exterior walls, advancing progress toward enclosure.
COURTYARD VIEW

April 2, 2026

COURTYARD VIEW
West view of the future student courtyard, designed as an inviting outdoor space for studying, relaxing, and gathering.
ROOFING MATERIALS BEING INSTALLED

March 9, 2026

ROOFING MATERIALS BEING INSTALLED
Roofing installation has begun, marking another key step in the construction process.
INTERIOR VIEW OF BUILDING

March 9, 2026

INTERIOR VIEW OF BUILDING
Interior progress continues to take shape - view from the north end of the building as structural framing and roof systems move forward.
OUTSIDE WALLS

February 19, 2026

OUTSIDE WALLS
Steel beams for the outside walls are taking shape on the south end of the building.
ROOFING STEEL STRUCTURE

February 19, 2026

ROOFING STEEL STRUCTURE
Another exciting milestone: reinforced steel beams for the roof are locked in and lifting our future classroom, conference room, and soils lab to new heights!
MAIN STEEL STRUCTURE IS UP

January 9, 2026

MAIN STEEL STRUCTURE IS UP
From blueprint to reality - watching our future rise beam by beam.
MAIN STEEL STRUCTURE IS UP

January 9, 2026

MAIN STEEL STRUCTURE IS UP
 
BUILDING FROM THE GROUND UP

October 29, 2025

BUILDING FROM THE GROUND UP
Setting the stage for a strong foundation with new footings taking shape.
GRAVEL IS DOWN AND LEVELED

October 15, 2025

GRAVEL IS DOWN AND LEVELED
The site is starting to take shape.
GRAVEL IS ROLLING IN

October 10, 2025

GRAVEL IS ROLLING IN
Semis unloading material that establishes a foundation for the project site.
FOUNDATION PREP

October 3, 2025

FOUNDATION PREP
Earthwork and grading in progress to create a solid foundation for the next phase.

Be the seed of progress--Give Now!